PROJECT INFORMATION
- Client : McArdle sport tec
- Type : Multiple Pitch construction
- Value : £200,000
- Completion Date : July 2018
CASE STUDY
The Project was for the creation of a New Training Facility for Reading FC.
- Removal of Topsoil and Sub-soil under Archaeological Supervision.
- Carry out the cut/fill to the required areas utilising GPS machine control for optimum accuracy.
- Trimming and preparation of Pitch Areas for 3G and stitched surfacing
- Resoiling to the natural pitches and surrounding areas to a specification required by the landscape contractor.
- On-going variations during the works meant constant surveying and quantity calculations were carried out by AJ Morris to ensure the most efficient use of available materials.