PROJECT INFORMATION

  • Client : Buckminster Management  
  • Type : Lake construction  
  • Value : £139,000
  • Completion Date : February 2015

CASE STUDY

A J Morris were commissioned to construct a 13,011 m³ lakes/pond as water feature for the estate.

Key tasks included;

Site clearance

Excavation/formation of lakes/ponds

Excavation & installation of Interceptor Land drainage

Landscape topsoil & reseed

Landscaping & plantation of fencing & trees for the future parkland.

A J Morris supplied all the machinery that was required to complete the project, including;

Volvo 35t Excavator

17t Excavator

Dumptrucks & Dumper

Caterpillar D6 with GPS

Fueling bowser

Combi Mess Unit

Tractors & Cultivators